Compaction formula (Subsidence Overlay): Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
Line 4: | Line 4: | ||
where | where | ||
: <math>S_{C}</math> is the calculated subsidence due to compaction. | |||
: <math>p_{c}</math> is the [[Peat fraction (Subsidence Overlay)|peat fraction]] of the respective grid cell | |||
: <math>tl_{c}</math> is the [[top layer thickness]] of the respective grid cell | |||
: <math>\Delta_h</math> The height increase as a result of the actions taken during a [[session]], such as the creation of [[levee]]s. | |||
: <math>t_{days}</math> is the number of days in a year times the current year being calculated. | |||
: <math>a_{peat}</math> is the first regression constant (0.015853041) for the effect of the peat fraction and time in days. | |||
: <math>a_{tl}</math> is the first regression constant (0.006617643) for the top layer thickness and time in days. | |||
: <math>a_h</math> is a regression constant (0.200468677) for the change in surface height, for example caused by added materials. | |||
: <math>b_{peat}</math> is the second regression constant (0.02348519) for the effect of the peat fraction. | |||
: <math>b_{tl}</math> is the second regression constant (-0.010061616) for the top layer thickness. | |||
This formula is based on provided expert data in the form of a reference table, indicating the amount of subsidence based on the parameters used in the formula above. The formula's results conform to the reference table to within an average of a tenth of the margin of error of the original table.<noinclude> | This formula is based on provided expert data in the form of a reference table, indicating the amount of subsidence based on the parameters used in the formula above. The formula's results conform to the reference table to within an average of a tenth of the margin of error of the original table.<noinclude> | ||
{{Template:SubsidenceOverlay_nav}} | {{Template:SubsidenceOverlay_nav}} | ||
</noinclude> | </noinclude> |
Revision as of 15:33, 9 February 2021
The amount of subsidence due to compaction is calculated by the following formula:
where
- is the calculated subsidence due to compaction.
- is the peat fraction of the respective grid cell
- is the top layer thickness of the respective grid cell
- The height increase as a result of the actions taken during a session, such as the creation of levees.
- is the number of days in a year times the current year being calculated.
- is the first regression constant (0.015853041) for the effect of the peat fraction and time in days.
- is the first regression constant (0.006617643) for the top layer thickness and time in days.
- is a regression constant (0.200468677) for the change in surface height, for example caused by added materials.
- is the second regression constant (0.02348519) for the effect of the peat fraction.
- is the second regression constant (-0.010061616) for the top layer thickness.
This formula is based on provided expert data in the form of a reference table, indicating the amount of subsidence based on the parameters used in the formula above. The formula's results conform to the reference table to within an average of a tenth of the margin of error of the original table.