The amount of subsidence due to compaction is calculated by the following formula: | The amount of subsidence due to compaction is calculated by the following formula: | ||
<math>S_{sub} = a_{peat} \cdot p_{x,y} + a_{tl} \cdot tl_{x,y} \cdot log10(t_{days}) + b_p \cdot p_{x,y} + b_{tl} \cdot tl_{x,y}+ a_h \cdot \Delta{h}</math> | <math>S_{sub} = ( a_{peat} \cdot p_{x,y} + a_{tl} \cdot tl_{x,y} ) \cdot log10(t_{days}) + b_p \cdot p_{x,y} + b_{tl} \cdot tl_{x,y}+ a_h \cdot \Delta{h}</math> | ||
where | where |
Revision as of 16:47, 8 February 2021
The amount of subsidence due to compaction is calculated by the following formula:
where
- is the peat fraction of the cell at coordinate (x,y)
- is the top layer thickness of the cell at coordinate (x,y)
- The height increase as a result of the actions taken during a session, such as the creation of levees.
- is the number of days in a year times the current year being calculated.
- is the first regression constant (-0.015853041) for the effect of the peat fraction and time in days.
- is the second regression constant (0.02348519) for the effect of the peat fraction.
- is the first regression constant (-0.006617643) for the top layer thickness and time in days.
- is the second regression constant (0.010061616) for the top layer thickness.
- is a regression constant (-0.200468677) for the change in surface height, for example caused by added materials.
This formula is based on provided expert data in the form of a reference table, indicating the amount of subsidence based on the parameters used in the formula above. The formula's results conform to the reference table to within an average of a tenth of the margin of error of the original table.